tower crane

Coventry Student Accommodation Starting to Take Shape

Two tower cranes have been delivered on a site in Coventry where the development of new student accommodation is taking place. UNINN Parkside Development’s scheme will see 502 en-suite, mix of studio & cluster bedrooms constructed within three towers – six, 13 and 19-storeys high. The 19th floor will house a

Read More »

First Tower Crane Arrives at Euston Station

The first tower crane has arrived at Euston Station, marking a major step forward for the transformation project. The project, which will be completed as part of the HS2 project, will deliver extra capacity to the station. HS2 will now progress with the demolition of One Euston Square and Grant Thornton

Read More »
Latest Issue
Issue 322 : Nov 2024

tower crane

Coventry Student Accommodation Starting to Take Shape

Two tower cranes have been delivered on a site in Coventry where the development of new student accommodation is taking place. UNINN Parkside Development’s scheme will see 502 en-suite, mix of studio & cluster bedrooms constructed within three towers – six, 13 and 19-storeys high. The 19th floor will house a rooftop lounge terrace. UNNIN Parkside Development has been working with Winvic Construction, who completed this recent milestone, to refine the design and solve engineering challenges for the last six months. “Winvic has been making excellent progress on Parkside and their knowledge of city-centre, high-rise developments is evident. Already there is a buzz about Coventry’s next luxury student accommodation provision and we look forward to welcoming students into their new rooms in summer 2020. Together with Winvic, we’re confident to exceed expectations,” said Andrew Jamieson, Managing Director of UNINN Parkside Development. So far, the piling for the 5 metre deep basement, which will provide a gym, laundry, cinema, karaoke room and communal lounge for tenants and a plant room/energy centre, has been completed. On the ground floor there is also planned a 100 m2 of retail space. Ground works are underway with the first pile caps and beams installed. Following this will be the storm water attenuation measures, blue roof tanking over basement areas and erection of the steel framed building will. A combination of brick slips and rainscreen cladding will make up the external façade’s striking design, and the interior will take shape with high quality finishes throughout, meeting the demands of the luxury student living market. Delivered on a turnkey service by Winvic, additionally comprising works to the existing highway and the creation of 160 bicycle spaces, the 95 week project will ready for habitation in August 2020.

Read More »

First Tower Crane Arrives at Euston Station

The first tower crane has arrived at Euston Station, marking a major step forward for the transformation project. The project, which will be completed as part of the HS2 project, will deliver extra capacity to the station. HS2 will now progress with the demolition of One Euston Square and Grant Thornton House, which stand above the entrance and exit to Euston’s old underground taxi rank. It is expected to take 10 months to complete. “HS2 will transform Euston, delivering much-needed extra capacity and better journeys for the 44 million people who use the station every year. We are already hard at work, delivering essential pre-construction work, including archaeology, utility diversions and of course, the demolition of the two Euston towers. The opening of the new taxi rank and the delivery of the project’s first tower crane is a significant milestone for HS2 and I would like to thank everyone involved in making it happen,” said HS2’s London Programme Director, Rob Carr. Early works contractor, a Costain and Skanska joint venture (CSjv), is currently working with expert subcontractors McGee, stripping out the interiors and erecting the scaffolding that will support acoustic screening around the buildings. “Costain and Skanska have successfully delivered many major infrastructure projects and are pleased to be delivering the HS2 enabling works programme in London. Our work continues to gather pace and constructing this temporary taxi rank to replace the underground taxi rank is vital to allow us to demolish the two large office towers at Euston,” commented CSjv’s Programe Director, Peter Jones. These landmark steps come after the station’s new taxi rank was opened to the public on Sunday 06 January. The new rank, delivered alongside TfL and Network Rail, has capacity for around 40 vehicles and has been designed to incorporate as many of the existing trees as possible.

Read More »