BDC

Search
BDC Magazine

grahams

GRAHAM underway with ‘world’s deepest nuclear clean-up’ at Dounreay

Construction and civil engineering specialist contractor GRAHAM is underway at a project to support the decommissioning and restoration of Dounreay, described as ‘the world’s deepest nuclear clean-up’. The Advance Transition Works Shaft & Silo Project (ATW S&S) are taking place at Dounreay in Caithness. The firm will be delivering the

Read More »

GRAHAM lands Chelmsford carriageway and bridge contract

The strength of GRAHAM’s highways and rail sector expertise has been recognised by Countryside Zest (Beaulieu Park) LLP and Highways England following the recent award of a design and build contract for the Chelmsford East Beaulieu S278 Works (RDR Phase 3) project. The works in Chelmsford, Essex, comprise of a

Read More »

Latest Issue

BDC 319 : Aug 2024

grahams

GRAHAM underway with ‘world’s deepest nuclear clean-up’ at Dounreay

Construction and civil engineering specialist contractor GRAHAM is underway at a project to support the decommissioning and restoration of Dounreay, described as ‘the world’s deepest nuclear clean-up’. The Advance Transition Works Shaft & Silo Project (ATW S&S) are taking place at Dounreay in Caithness. The firm will be delivering the Civils and Structural works on behalf of Nuvia, acting as sub-contractor and an influential partner on the scheme.  Background The Dounreay Shaft in Caithness was originally constructed in 1956 as a means of removing waste from the Dounreay site liquid effluent discharge tunnel excavation. The Shaft goes approximately 65m deep underground and was used to store radioactive waste until 1977. A connecting ‘stub’ tunnel linked the base of the Shaft to the effluent discharge tunnel. This was sealed in 1956 by the construction of a concrete plug to produce a water- tight seal, before the Shaft was then allowed to flood with groundwater. Disposals to the Shaft ended following an explosion occurred in May 1977 and the facility has been under care and surveillance ever since. Decommissioning and restoration Dounreay Site Restoration Limited (DSRL) is currently working to decommission and restore the site. Part of this Programme is the D3300 Project, to retrieve, process and package waste from the Shaft to render it suitable for long-term storage and future disposal. During the project, new headworks will be constructed over the Shaft that will contain remote handling equipment to retrieve the solid and sludge waste. GRAHAM’s project team will be delivering and supporting the following scope of works as part of the project: Establish secure Site Boundary and site accommodation – provision of hoarding, fencing and barriers around the construction areas and any site accommodation facilities. Facilitate safe (as low as reasonably practicable) and efficient (best practical means) access to D1225 to prepare for dismantling and breakout of the existing Shaft headworks (steel platform, concrete cover slab, concrete capping slab). Dismantling the existing D1225 enclosure and constructing an appropriate robust replacement facility. The replacement must fully integrate with D3300 (construction to follow later). Installing and protecting coordinated services diversions and replacements that will provide for continued interim functioning of D1225 and integrate with the future D3300. Installation of the D3300 Shaft Extension Module lower section (SEM 1). Accommodating the future constructability of D3300 Process Cell equipment and structures. Subsequent D3300 construction to be safeguarded from potential releases of radiation/contamination from the Shaft. Peder Andreasen, Contracts Manager for GRAHAM, said: “We’re excited to be beginning work at this hugely important project at this historic nuclear clean-up scheme. “Our nuclear sector expertise and safety critical approach will be vital in the delivery of the ATW S&S scheme and enable us to safely prepare the shaft headworks and provide a secure enclosure by undertaking these hazardous and challenging works.”

Read More »

GRAHAM lands Chelmsford carriageway and bridge contract

The strength of GRAHAM’s highways and rail sector expertise has been recognised by Countryside Zest (Beaulieu Park) LLP and Highways England following the recent award of a design and build contract for the Chelmsford East Beaulieu S278 Works (RDR Phase 3) project. The works in Chelmsford, Essex, comprise of a new viaduct over the Great Eastern railway and A12 and carriageway works (RDR Phase 3) linking into the Boreham Interchange. The scheme, which is being directed by Countryside Zest in partnership with Highways England, is subject to a single-phase procurement process, although the works will be split into two phases. The first, a £1.4m-valued ‘Stage 1 Pre-Construction Services’ appointment, will focus on design development in order to secure technical approval from the relevant authorities, including Highways England and Network Rail. Detailed site surveys and investigation, plus a robust assessment of possession requirements and timescales, represent complex elements of this phase. Stage 2 ‘Construction’, with an estimated value of £11.8m, will then involve the commencement of an engineering and construction programme based on the agreed outputs from Stage 1. Track record GRAHAM has a proven track record in the Chelmsford area having completed the award winning A138 Chelmer Viaduct – a £32m strategic highway, which has increased transport capacity and significantly improved journeys for motorists, cyclists and pedestrians. GRAHAM’s Managing Director for Civil Engineering, Leo Martin, is looking forward to his team delivering a similar high-calibre piece of infrastructure as part of the Chelmsford East Beaulieu S278 Works project. “This contract award is a tremendous result for us and it once again underlines our combined approach and reputation for excellence in both the highways and rail sectors,” said Leo. “The first phase of this contract requires a fully-coordinated design methodology that meets the approval and standards of Highways England and Network Rail. We have enjoyed long-term relationships with both organisations and fully understand their technical requirements. “I’m confident that our existing knowledge and design expertise will not only meet, but exceed, their expectations, which will ensure a seamless transition to Stage 2 and the beginning of the construction works. “As we proved with the A138 Chelmer Viaduct, we use our expertise and creativity to identify and implement solutions that reduce cost, drive efficiency and enhance outcomes and therefore we are looking forward to replicating this approach for the Chelmsford East Beaulieu S278 Works project.” Phasing The approved phasing of the development requires the initial stopping up of the existing Generals Lane highway and the subsequent demolition of the bridge structure, which currently crosses the Great Eastern railway line in advance of the commencement of the RDR Phase 3 carriageway and bridge construction. The design requirements for the project include a radial distributor road, a bridge structure crossing the Great Eastern mainline and drainage and services. Design work is well under way and is expected to be completed in 2020.

Read More »