Collett Complete Stage Two of the Saltend Power Station Project
Collett Complete Stage Two of the Saltend Power Station Project

Following on from the delivery of a 100Te gas turbine rotor to Saltend Power Station, Hull, the Collett Team were once again appointed by Expeditors to undertake transport of the original turbine.

The Saltend CHP (Combined Heat & Power) Power Station generates power efficiently using exhaust heat from the gas turbine to produce steam which, in turn, drives a steam turbine on the same shaft, increasing the energy output of each generating unit and producing more power for less fuel. 

The Collett Team, on behalf of Expeditors, were tasked with this two-stage project, firstly delivering a new 100 Tonne gas turbine rotor to the CHP station, before removing the old module to allow for refurbishment.

Having undertaken the delivery and positioning of the new 100 Tonne gas turbine rotor from the Antonov 124 aircraft at Doncaster Airport the previous month, the original unit remained in storage at the power station awaiting transport and transshipment overseas.  With the new turbine now in position and operational, our Team were on hand to begin stage two of the project, to extract and remove the old turbine rotor from the power station site.

Stored on stools since its removal, we arrived on site ready to load the cargo.  Utilising a 12-axle drawbar trailer, our Transport Team reversed directly under the module before employing the hydraulic capabilities of the trailer to raise the trailer bed.  This, in turn, lifted the 100 Tonne turbine free of the support stools, loading directly to the trailer.  Once secured, the cargo left Saltend Power Station, under escort, for the short journey to our Goole Heavy Lift depot for secure weekend storage.

As Monday morning arrived, the loaded cargo took to the road again.  Continuing to travel under escort, the convoy made the short 50-mile journey to the CLdN Terminal at North Killingholme, north-west of Grimsby, ready for short sea shipping to Rotterdam.

Still loaded to a 8×4 MAN TGX equipped with a drawbar 12 row trailer, and accompanied by the driver and steersman, the gas turbine rotor arrived at the Port of Rotterdam.  After rolling off the CLdN vessel, the cargo was then transshipped from the trailer by 500Te mobile crane for onward shipment to Antwerp.

With all transshipment operations complete, the our Team hopped back on the ferry, returning to Goole and completing stage two of the Saltend Power Station project.

LinkedIn
Twitter
Facebook
Pinterest
WhatsApp
Email
Latest Issue
Issue 322 : Nov 2024