We’re half way there! HS2’s Northolt Tunnel under the capital is 50% complete
We’re half way there! HS2’s Northolt Tunnel under the capital is 50% complete

HS2’s tunnelling team are celebrating completing half of the 8.4-mile twin bored Northolt Tunnel underneath London.

Four tunnel boring machines (TBM) are being used the complete the tunnel that will carry high-speed trains between HS2’s super-hub station at Old Oak Common, west London, and the outskirts of the capital at West Ruislip.

The machines will excavate 16.8 miles of tunnel overall – two bores over the 8.4-mile length – making it the second longest tunnel on the new railway after one recently excavated beneath the Chiltern Hills.

The first machine, named Sushila after a local teacher, was launched eastwards from West Ruislip in October 2022. This was followed one month later by TBM Caroline, named after astrologer Caroline Herschel, which is used to excavate the adjacent tunnel.

Both will complete 5 miles of the route, finishing their journeys at the Green Park Way vent shaft in Greenford – just over half way – where they will be lifted out.  

In February this year, TBM Emily, which is named after Emily Sophia Taylor, began its journey west from HS2’s Victoria Road Crossover Box site near Old Oak Common towards Greenford. She was joined by the fourth machine, named Anne, after Lady Anne Byron, in May. They will both complete 3.4 miles of the tunnel.

Combined, the four machines have now travelled over 8.4 miles – half of the total distance for the twin-bored tunnel. The completion of each tunnel drive will be staggered as they reach the final destination at Green Park Way, with the first TBM, Sushila, arriving later this year.

Each machine operates like an underground factory, excavating the tunnels, lining them with pre-cast concrete tunnel segments, grouting them into place before moving forward at an average speed of 16 metres per day. Teams work around the clock below ground on the TBMs along with teams on the surface supporting them.  

Marking the significance of the tunnelling milestone, Malcolm Codling, Client Director for HS2 Ltd, said:

“Our London tunnels team are making significant progress taking HS2 from design to reality underneath the capital, building Britain’s new transformational low carbon railway. Completing half of the Northolt Tunnel has come after years of work from the team and we are now looking forwards to the TBMs reaching the end of their journeys, with the first arriving at Green Park Way in Greenford later this year. “

As the TBMs progress, other vital features of the tunnel are put in place such as cross passages, vent shafts and headhouses. Along the Northolt Tunnel there are five shafts and headhouses which will provide ventilation systems and emergency access to the tunnel when in operation.  

Between them, the quartet of machines have excavated nearly 2 million tonnes of earth.

The excavated material is being put to beneficial reuse. Around the West Ruislip portal, it is being used around the Copthall Green Tunnel, to remodel a nearby golf course that has been impacted by HS2’s tunnelling and is being used sustainably to create new green spaces in the Hillingdon area surrounding the new railway.

London Clay removed from the Victoria Road Crossover Box side of the tunnel, is being taken to the London Logistics hub using a spoil conveyor. From there it is taken by rail to beneficial reuse sites across the UK in Rugby, Kent and Cambridgeshire. The logistics hub has now transported over 2 million tonnes of materials to these sites, which are being used to backfill quarries to support housing developments and build wildlife areas for birds.

The Northolt Tunnel is being built by a joint venture formed of the companies Skanska, Costain and STRABAG (SCS). The same JV will also construct the Euston Tunnel eastward from Old Oak Common to the centre of London.

James Richardson, Managing Director of Skanska Costain STRABAG joint venture, said:

“Reaching the halfway point of our tunnelling programme for the Northolt Tunnel demonstrates the huge progress achieved to date on one of the most complex and ambitious programmes embarked upon in the UK. Alongside the tunnelling operations we are now moving into the fitout stage of the works in readiness for track and rail systems to be installed.

“At Old Oak Common, we are gearing up to assemble and install our final two TBMs, ready to take the high-speed line into central London.”

In May, HS2 revealed that across the route between London and the West Midlands, half of all the twin bored tunnel had been complete highlighting the significant progress HS2’s 31,000 strong workforce have made in constructing Britain’s new high speed rail line.

Two of the tunnels are now complete – one stretching for 10 miles under the Chiltern Hills and another one-mile in length beneath Long Itchington Wood in Warwickshire. Two others remain under construction – the Northolt Tunnel in London and the 3.5-mile Bromford Tunnel in the West Midlands taking the line into central Birmingham.

Preparations to bore the final tunnel between Old Oak Common station and Euston are underway with two further TBMs due to arrive in the UK this summer ready to be assembled in the underground box at the station site. Timings and funding for the construction of the Euston Tunnel are being confirmed with government.

When complete, HS2 will improve connections between London and the West Midlands, with trains running further north on existing lines. The new high speed railway will create quicker and more reliable journeys, driving economic growth while crucially freeing up space for more local trains on the most congested part of the existing West Coast Main Line.

Building, Design & Construction Magazine | The Choice of Industry Professionals

LinkedIn
Twitter
Facebook
Pinterest
WhatsApp
Email
Latest Issue
Issue 324 : Jan 2025