£3bn early works push aims to unlock historic Parliament restoration
New public underground access to Parliament forms part of the restoration and renewal plan

MPs and Peers are being urged to approve a £3bn programme of early works designed to stem the rising cost of repairs at the Palace of Westminster and pave the way for the largest restoration project in its history.

A new report from the Parliamentary Restoration and Renewal Client Board sets out a proposed seven-year phase one programme of enabling and preparatory works. The aim is to reduce reliance on costly reactive maintenance, stabilise ageing systems and buy time while Parliament reaches a final decision on how the main restoration should be delivered.

Under the plan, preparatory work would begin immediately, narrowing the long-running debate to two remaining delivery options by 2030.

The first option would see both the House of Commons and the House of Lords fully decant from the Palace, allowing the building to be stripped back and restored in a single, continuous programme. While politically challenging, this approach is considered the safest and most cost-effective, with an estimated duration of up to 24 years and a projected cost of close to £12bn.

The alternative is an enhanced maintenance and improvement option, which would keep Parliament operating within the Palace while works are carried out in multiple phases. This approach would require MPs and Peers to move between temporary chambers, including relocating the House of Lords to the QEII Centre for up to 13 years. The phased approach would significantly extend the programme, potentially running for as long as 61 years, with costs rising towards £39bn.

CategoryFull decantEnhanced maintenance and improvement (EMI+)Comparison
Total cost£8.4–11.5bn£11.8–18.7bnEMI+ significantly more expensive overall
Total duration19–24 years38–61 yearsEMI+ takes roughly double or more
House of Commons chamber decant8–10 yearsUp to 2 years in the Lords chamberLonger Commons relocation under full decant
House of Lords chamber decant12–15 years8–13 years in the QEII CentreDecant periods broadly similar
Parliamentary businessDelivered with some reduced provision, may require changes to ways of workingDelivered with some reduced provision which may require changes to ways of workingOperational impact similar
Health, safety and fire riskLowest level of riskHighest level of risk of the optionsFull decant safer
Security riskLowest level of risk in the PalaceHighest level of risk in the PalaceFull decant offers strongest security

The Client Board warns that further indecision will continue to cost taxpayers heavily. Each year of delay is estimated to add around £70m in wasted option development and reactive maintenance, with construction inflation adding hundreds of millions more to the eventual bill.

If approved, procurement for a series of strategic partners covering programme management, technical consultancy and delivery would begin later this year, with appointments expected in 2027. These partners would be tasked with delivering the early works and developing detailed designs, costs and programmes for both delivery options ahead of a final decision by both Houses later in the decade.

Phase one would include a number of major enabling projects, such as the construction of a temporary Thames jetty and cofferdam to move materials by river, underground works to release space for new services, early masonry repairs and restoration of key courtyards.

The programme would also see temporary power, water and utility systems installed, allowing life-expired infrastructure to be safely taken offline in future phases. Significant remodelling works at the QEII Centre are also planned to support decant arrangements and improve operational resilience during the restoration programme.

Overlapping services located in the Palace basement

Building, Design & Construction Magazine | The Choice of Industry Professionals

LinkedIn
Twitter
Facebook
Pinterest
WhatsApp
Email
Latest Issue
Issue 337 : Feb 2026