BDC

Search

Trades : Temporary Works News

Eight-sided support from Groundforce Shorco

Eight-sided support from Groundforce Shorco

Groundforce Shorco has supplied a space and time-saving solution to a project at a wastewater treatment works in Kent. Main contractor Clancy is installing a new storm tank for Southern Water at its Westbere wastewater treatment works near Canterbury. The new storm tank will accommodate surface water surcharges during periods

Read More »
Doka Leads with Smart Sensor Technology

Doka Leads with Smart Sensor Technology

Doka, one of the world’s leading experts in formwork and scaffolding, has been a reliable partner for years providing digital solutions for increasing efficiency and safety on construction sites. With the introduction of the new DokaXact Load & Pressure sensors, Doka now enables real-time monitoring of the pouring process. Choosing

Read More »
Doka boosts construction site safety with Xsafe Catch Fan

Doka boosts construction site safety with Xsafe Catch Fan

With its new Xsafe Catch Fan, Doka is redefining benchmarks for construction site safety. The impressive system adds an innovative safety solution and improves efficiency minimising the workforce necessary for assembly and application. Falling material, tools, or debris are a considerable risk on construction sites. Doka provides a safe, high-quality

Read More »
Groundforce Shorco delivers bespoke solution for major Dublin dig

Groundforce Shorco delivers bespoke solution for major Dublin dig

Groundforce Shorco has supplied a bespoke support system for a major excavation in Dublin. Contractor Bennett Construction is building a new eight-storey campus building in Dublin city centre for the Royal College of Surgeons in Ireland (RCSI). Two of the building’s eight storeys are below ground, which means the site

Read More »

Latest Issue

BDC 319 : Aug 2024

Trades : Temporary Works News

Eight-sided support from Groundforce Shorco

Eight-sided support from Groundforce Shorco

Groundforce Shorco has supplied a space and time-saving solution to a project at a wastewater treatment works in Kent. Main contractor Clancy is installing a new storm tank for Southern Water at its Westbere wastewater treatment works near Canterbury. The new storm tank will accommodate surface water surcharges during periods of heavy rainfall, helping to prevent the discharge of raw sewage into the nearby River Stour. The tank comprises six precast concrete rings of 15m diameter installed one on top of the other to a depth of 6.5m. Each ring is made up of 16 interlocking caisson segments. The concrete segments are made by FP McCann and supplied through heavy-side materials distributor Keyline. To accommodate this tank, Clancy will dig an octagonal excavation to a depth of 7m. To support this, Groundforce Shorco is supplying 120 interlocking 6m GFI steel sheet piles driven to a depth of 6m using an excavator-mounted vibrating hammer Mueller MS4 supplied by Groundforce’s Piletec division. Once Clancy has installed the sheet piled cofferdam, it will excavate to a depth of about 1m at which point the top of the cofferdam will be braced using Groundforce Shorco’s modular hydraulic Mega Brace system. Clancy will then continue to excavate to formation layer before casting the base slab for the storm tank. “The excavation is octagonal because it makes no sense to dig a rectangular hole for a circular tank,” explains Clancy project manager Oliver Smart. “The octagonal excavation reduces the amount of muck away and requires less kit and less materials,” he adds. The excavation can follow the perimeter of the concrete tank closely while providing sufficient space to accommodate the bracing. “It’s a challenging design and excavation but the Mega Brace adaptability made it easier,” explains Groundforce Shorco area sales manager Arpad Nagy. “The Mega Brace is a modular bracing system and is very adaptable. It’s easy to install whatever the shape of the excavation and in this case, an octagonal excavation requires less equipment than a square one would. With the octagonal shape the muck away has been reduced by 20%, in this case 200m3. The excavation has been reduced with 10lm worth of sheet piling and 30lm worth of bracing. On this case we’ve managed to reduce the carbon footprint which helps reduce the environmental affect.” Groundforce is one of Clancy’s preferred suppliers of temporary works equipment. “I’ve worked with them on several projects,” says Oliver Smart. “The kit is great and Groundforce has a good design capability. They are providing on-going support and technical advice on this project.” Building, Design & Construction Magazine | The Choice of Industry Professionals

Read More »
Doka Leads with Smart Sensor Technology

Doka Leads with Smart Sensor Technology

Doka, one of the world’s leading experts in formwork and scaffolding, has been a reliable partner for years providing digital solutions for increasing efficiency and safety on construction sites. With the introduction of the new DokaXact Load & Pressure sensors, Doka now enables real-time monitoring of the pouring process. Choosing the right concrete pouring speed depends on many external factors, such as the weather or the concrete mix. The real-time data from the new wireless DokaXact sensors ensure that concrete is poured as fast as possible while ensuring safety and the best possible concrete quality – even when using more climate friendly, CO2-reduced concrete mixes. DokaXact sensors are robust, waterproof, dustproof, and can be easily connected to the user’s smartphone via Bluetooth. “We aim to support our customers with digitalization in order to optimize construction projects. With data generation and real-time analysis, we are taking a further step towards smart formwork, ensuring greater efficiency and safety in concreting,” says Doka CEO Robert Hauser. Digital precision directly from the formwork DokaXact Load offers a solution for monitoring formwork loads. The sensors are designed for straightforward installation on standard tie systems, thus providing reliable data on tie loads for the first time. No special tools or major installation work are required. The DokaXact pressure sensor is designed for monitoring fresh concrete pressure. Installation is quick and easy, because it can be mounted directly on the plywood and requiring only a 26 mm hole. The data from both sensors is visualized in real time in the user-friendly DokaXact app directly on a smartphone. The intuitive user interface allows for simple and independent operation. The DokaXact web portal also provides detailed information and transparent documentation on the project. The new DokaXact sensors offer significant future applications, particularly for large-scale infrastructure projects such as tunnels. However, just as the reliable formwork systems from Doka are suitable for a wide range of concrete construction sites, so too are the DokaXact sensors. They can be used in the energy sector, in residential or commercial construction, and in projects with critical anchor loads or high, single-sided walls or pillars. As Hauser notes, “Wherever mission-critical data is required, projects can be optimized with DokaXact.” Achieving faster pouring times with DokaXact Thanks to data-based decisions, DokaXact sensors are already ensuring increased precision on the first construction sites in North America and Germany, as well as in other regions. For example, with the construction of sanitary sewer manholes in Mississauga, Ontario (Canada), where the use of DokaXact sensors reduced pouring time by five hours. “By monitoring the pressure with DokaXact, we were able to optimize the design and precisely control the load on the formwork, without having to produce expensive customized solutions,” says Michael Genz from Sales Doka USA. DokaXact will soon be launched in other countries and regions including the UK, Austria, Switzerland and Norway. Building, Design & Construction Magazine | The Choice of Industry Professionals

Read More »
DOKA FORMWORK SETS STAGE FOR SPECTACULAR REGENERATION OF HISTORIC SOUTH LONDON DISTRICT

Doka formwork sets stage for spectacular regeneration of historic South London district

Several Doka SKE50 plus hydraulic and Xclimb 60 crane-lifted climbing formwork systems are being used to construct four new town centre towers that are at the heart of   Southwark Council’s Elephant and Castle redevelopment programme. The development will transform an area of South East London that was once compared to Piccadilly Circus on account of its dynamism and vibrancy. The huge works programme, which is being carried out in three phases, will lead to the creation of a new town centre. It will include 1,000 new homes, an upgraded Elephant and Castle tube station and the building of a cutting-edge campus for nearby London College of Communication, part of UAL University of the Arts London.  Contractor Morrisroe selected Doka to provide its design expertise and innovative hydraulic climbing formwork for the construction of the concrete cores that will form the three of the developments multi-storey tower blocks. Each block will comprise a standard concrete finish featuring Doka Framax Xlife panels. These are being installed using Doka’s SKE50 plus hydraulic climbing formwork. The crane-independent system includes an all-round enclosure that makes for safe, weather-shielded working at any height. Such is the SKE50’s robustness and reliability, it facilitates the floor-by-floor lifting of internal-external materials whilst protecting operatives carrying out the rebar process in preparation for casting concrete. The all-hydraulic crane-less climbing method optimises construction workflows by allowing greater flexibility in respect of cycling the SKE50 units’ repositioning. The fourth core, which was the first one to come out of the ground, was constructed using the Doka Xclimb 60 crane-lifted solution. This system was chosen primarily because this tower was much lower than the others. Additionally, it was originally specified as a cost-effective option due to the fact that the slab was programmed to follow, and it was completed before the cranes were too heavily utilized on the rest of the vast project. As well as reviving Elephant and Castle as a thriving social, cultural, and commercial hub, it’s estimated the town centre development will create 1,230 construction jobs over the ensuing decade. Approximately 2,000 full-time jobs will ultimately be created upon the wider development’s scheduled 2030 completion. This is a blue-chip project in a characterful, historical area of London that thanks to Doka and a myriad of skilled, visionary stakeholders, will see Elephant and Castle prosper as a redeveloped cultural hub. Building, Design & Construction Magazine | The Choice of Industry Professionals

Read More »
Doka Slipform exceeds expectations with rapid, high-precision construction of city redevelopment

Doka Slipform exceeds expectations with rapid, high-precision construction of city redevelopment

Doka Slipform solutions ensured the rapid, efficient construction of a high-rise concrete core that is integral to a standout redevelopment in London’s financial district. The project involves the construction of 2 Aldermanbury Square, a 12 storey, grade A office building with market-leading sustainability credentials located in the City of London. The redevelopment will increase its lettable area significantly from 180,000 sq ft to 320,000 sq ft and incorporate public realm and amenity improvements designed to positively impact the local area. Selected by specialist concrete sub-contractor Keltbray to construct the building’s 65-metre core, Doka took an innovative approach to the formwork specification and assembly in order to accommodate 12 lift shafts, two lobbies and two staircases within the core’s construction.  Architectural demands led to the walls of the two cores being constructed using Doka’s Slipform system. The project’s size and scale demanded a solution that facilitated a safe build at rapid speed. Doka Slipform delivered on both counts. The system enabled the pouring of about 80m3 of concrete per working day on the vast concrete structure. An additional benefit of Doka’s Slipform system was its easy maintenance and cleaning capability, enabling its readiness to begin effective operation during the strict council-allotted time provided. Up to 11 deliveries of ready mixed concrete per day were required in the construction process, resulting in Doka’s Slipform system exceeding the originally planned ‘climb’ target of 1.7 metres per day by an additional 0.3 metres. Doka’s excellent working relationship with Keltbray was key to the concreting aspect’s success. Even before the commencement of site activities, the partnership began with Doka’s specialist Slipform supervisor overseeing pre-assembly works in Keltbray’s yard facilities, an alternative approach to Doka traditionally offering pre-assembly works and labour from its own yard.   With space severely restricted on-site, offsite assembly and delivery of the formwork was crucial in terms of operational safety, speed and efficiency. As part of its all-around customer service offering, Doka’s technical team attended the site to oversee the Slipform process and offer guidance when required.  Doka’s innovative incorporation of two concrete placing booms onto the rig via one concrete line was requested by the contractor and the move was instrumental in facilitating a smooth concreting process. Unique to Doka’s Slipform equipment is its compatibility with a variety of Doka proprietary rental equipment. Potentially, this means customers can reuse equipment on a range of Slipform projects, which has long-term benefits in terms of cost and sustainability. The Aldermanbury Square project offered further valuable proof of Doka’s ability to design and supply formwork solutions for projects ranging in profile and complexity. The team’s skill in meeting ad-hoc challenges throughout the programme ensured the core’s time-efficient, high-precision completion. Building, Design & Construction Magazine | The Choice of Industry Professionals

Read More »
Doka Formwork and hydraulic climbing system facilitates constrained capital building project

Doka Formwork and hydraulic climbing system facilitates constrained capital building project

High specification formwork, from Doka, along with its innovative hydraulic climbing system, ensured the safe, speedy delivery of a specialist concrete core for a standout new office building in central London. The City of London’s urban planners were given the green light to Edenica, a 12-floor, 60-metre-high building for developer BREO Hundred. The new development is situated on the same site as the public house formerly known as the “Mucky Duck”, which was a prominent destination for sports journalists when the UK’s national newspaper publications were based in neighbouring Fleet Street. This building occupies a 140,000 ft2 site in Fetter Lane, with a pedestrian route and a sunken garden forming part of the development along with additional space for a new pub, more recently named “The White Swan”. Chair of the Planning and Transportation Committee at the City of London Corporation, Alastair Moss, said the scheme in Fetter Lane “represented strong ongoing developer confidence in the future of the City as a leading location” and an area to “spend time with friends, family and colleagues”. Main contractor Mace, is overseeing Edenica’s development, with the building’s core being formed and completed by specialist concrete sub-contractor Keltbray. It was achieve using Doka’s Top 50 wall formwork, supporting the need for a special high class architectural finish, and the Doka Framax systemised wall panels for the core’s primary solution. The large-area Top 50 formwork allowed for the design and pre-assembly of bespoke shuttering, which was essential to achieving the architect’s specialist wall pattern finish for the Edenica building, in good time and to the highest standard. Edenica’s central London location restricted the use of cranage due to strict site boundary limits being imposed to protect the surrounding live, public environment. It called for a hydraulic climbing system, which is where the Doka SKE50 plus system overcame the challenges presented by the serious lack of operational space. Firstly, the crane-independent SKE50 plus proved ideal for providing a coordinated anchor pattern around the form ties to facilitate the core’s external design pattern. Thanks to pre-project design capabilities from the Doka team, the anchors were concealed within the raised floor zones to avoid disrupting the finished wall’s aesthetic. The SKE50 plus’ strength and all-hydraulic performance was also key to its other vital function as part of the Edenica project. The new steel frame building contained a separate unsupported riser. It meant an innovative approach was needed to install temporary diagonal support struts at each floor to give the main core the structural strength to incorporate the non-standard element of the building’s design. Due to limited crane access, a winch was attached to the SKE50 plus’ platforms, enabling the struts to be lifted from a minus two level platform – designed by Doka – and affixed to the concrete core. The Edenica programme showcases how the Doka specialist formwork, paired with design expertise, effectively enabled the meeting of complex and demanding project challenges to ensure the safe erection of its concrete core within the clients’ seven-month timeframe. Furthermore, Doka’s formwork expert’s site visits ensured its pre-assembled platforms’ correct implementation. Along with the company’s productive consultations with Keltbray, it offered a fine demonstration of Doka’s all-round service delivery and commitment to a successful project outcome.  Building, Design & Construction Magazine | The Choice of Industry Professionals

Read More »
Innovative Base Screens speeding up construction programmes across the country

Innovative Base Screens speeding up construction programmes across the country

Base Structures are announcing a new offering from its tensile fabric experts, Temporary Weatherproof Screening, promising to speed up building programmes and mitigate against weather delays on site. Base Screens are a new product that provide a unique and efficient solution for weatherproofing requirements on construction sites. Quick to install and demount, they are customisable to meet specific site conditions, which presents contractors with the chance to remove conventional cladding from a programme’s critical path. This accelerates the construction schedule and allow teams to progress with fit out works, staying ahead of any delays that the changing climate may bring. Andy Traynor, Director at Base Structures and Head of Installations and Health & Safety, said: “Our in-house expertise and engineering capabilities mean that we can design, manufacture and erect temporary weatherproof screens very quickly and to fit an existing structure, safeguarding construction works from external elements. By installing screens early in a project, we can provide a bespoke solution to ease the installation, movement and removal of the screens at various points in the building programme at specific fixing points. This means that there’s no requirement for scaffolding, minimising any potential for damage to works that have already been completed. We’re delighted to have been able to offer this innovative solution to several happy clients across the country, and with an increase in this kind of work, Base Structures are well placed to help teams find solutions to keep building programmes on track despite the rainfall and weather challenges we’ve seen this springtime.” Base Screens are made of PVC fabric that can cover large areas. They’re durable, easy to clean, fire retardant and a low-risk option, offering a less labour-intensive and safer solution than other more traditional weatherproofing options. Base Structures have produced case studies of their work in this area, which can be found via the links below: Project Resilience – Base Structures Engineered Temporary Weather Screens Dublin Terminal 2 Temporary Works Screens They have also produced a blog post detailing some of the benefits of adding weatherproof temporary screens to your next building project. For more information, case studies, images or quotes, please contact mail@basestructures.com or visit the contact us page. Building, Design & Construction Magazine | The Choice of Industry Professionals

Read More »
Doka boosts construction site safety with Xsafe Catch Fan

Doka boosts construction site safety with Xsafe Catch Fan

With its new Xsafe Catch Fan, Doka is redefining benchmarks for construction site safety. The impressive system adds an innovative safety solution and improves efficiency minimising the workforce necessary for assembly and application. Falling material, tools, or debris are a considerable risk on construction sites. Doka provides a safe, high-quality catch fan system, which can be deployed and re-positioned quickly in just a few simple steps. Maximum flexibility Two particularly clever mechanisms are at the heart of Doka’s development. In combination with the innovative suspension of nets, the easy-lock system enables efficient installation via a snap mechanism of the floor shoe: A safety lever secures the vertical tube of the Xsafe Catch Fan in place; without the need to use fastening couplers. With the quick-folding mechanism, the net is folded from the upper slab by pulling on a rope. This new solution does not require multiple workers working simultaneously on two levels but enables the net to be folded by just one user, minimising manpower and crane time during re-positioning and cleaning. All-round winner The vertical extensions of the Xsafe Catch Fan are specifically designed to meet the customer’s needs: Square tubes do not require hole alignment when securing with bolts. Once assembled on the ground, the Xsafe Catch Fan can easily be lifted and quickly re-positioned from floor to floor without adjustment to the vertical extensions. “With the development of the Xsafe Catch Fan, we identified the potential to provide additional safety on construction sites. Customers benefit from efficient and simple workflows, allowing them to focus fully on the essentials of day-to-day construction site operations,” says Thomas Lattacher, Product Manager, Xsafe Catch Fan. Continued innovation Since the beginning of 2024, the Xsafe Catch Fan also features a unique solution for areas sometimes difficult to cover. With it’s innovative, foldable and EN 1263 compliant corner solution, Doka sets new standards in protection against falling objects. With few additional parts, customers can create corner units from their existing stock or get full packages straight from their local Doka partner. Building, Design & Construction Magazine | The Choice of Industry Professionals

Read More »
Paratop Bridge Formwork is Core to the Rapid, Reliable Formation of Road Link to Cancer Care Centre

Paratop Bridge Formwork is Core to the Rapid, Reliable Formation of Road Link to Cancer Care Centre

Doka’s versatile ParaTop bridge formwork provided the ideal solution for the rapid, high-specification creation of concrete decks that are integral to providing patients with a crucial new transport link to a cancer care centre. The 56-metre single-span bridge will improve road access to the Velindre Hospital in Cardiff. Known as the ‘Hospital of Hope’, the facility offers specialist and complex cancer services to more than 1.5 million people in south east Wales and beyond. Doka’s ParaTop bridge formwork was selected by principal contractor, Walters, as the ideal system for the rapid, effective formation of the bridge’s concrete parapets. ParaTop was created using modular principles, whereby the system can be adapted to specific applications. Its strength is its versatility, allowing ParaTop to be fixed to concrete or steel superstructures. The system contains an innovative insert-shoe, making it simple to erect whilst its cantilever formwork makes it easy work for cranes to install and lift when required via hard-plated insert-cones. ParaTop removes the need for platforms or scaffolds beneath the superstructure and fewer bracket planes are also required. Erection and dismantling times can be significantly reduced by using bolted, rather than threaded joints. In addition, ParaTop’s cantilever arm formwork eliminates the threading of tie rods in readiness for the concrete pouring process. For the Velindre Hospital Bridge project, the ParaTop bridge formwork was installed by Wyndham Construction. It was attached, via crane, to the bridge’s 2.3 metre-high, 1.2 metre-wide Corten steel beams. In total, the composite ladder beam-type plate girder bridge comprises 293 tonnes of steel. Rhodri Jones, Sub Agent at Walters, said Doka’s ParaTop bridge formwork ensured an installation that was rapid and issue-free. “The system hooked on quickly and easily to the bridge’s beams” he said. “The dismantling process was equally as straightforward, requiring the removal of just three bolts in what was a very simple and time-effective process. Overall, we’re delighted with the ParaTop bridge formwork’s performance on this incredibly worthwhile project for south east Wales.” The Velindre Hospital Bridge means visitors can travel to the cancer care centre, which is staffed by clinicians and scientists who are world leaders in their field, with greater convenience and comfort. Doka is proud to have supplied the high-quality formwork that is core to the structure’s long-term stability. Building, Design & Construction Magazine | The Choice of Industry Professionals

Read More »
Groundforce Shorco delivers bespoke solution for major Dublin dig

Groundforce Shorco delivers bespoke solution for major Dublin dig

Groundforce Shorco has supplied a bespoke support system for a major excavation in Dublin. Contractor Bennett Construction is building a new eight-storey campus building in Dublin city centre for the Royal College of Surgeons in Ireland (RCSI). Two of the building’s eight storeys are below ground, which means the site is currently occupied by a deep excavation more than 50m long and 30m wide. Modular hydraulic equipment supplied by Groundforce Shorco is supporting the concrete secant-piled retaining wall while Bennett Construction completes the excavation and installs the reinforced concrete basement slab. Although the excavation is roughly rectangular in plan, it includes several irregularities that complicate the engineering of the support solution. Lateral forces impose geotechnical loads varying between 215kNm and 300kN/m which are supported by Groundforce Shorco’s MP150 and MP250 hydraulic props via a waling beam comprising the company’s modular Mega Brace system. However, where the shape of the excavation does not allow the use of standard equipment, bespoke beams and props have been designed and supplied to ensure that all of the concrete secant piles remain fully supported. Five MP250 props support the middle of the excavation, spanning almost 30m. These props are fitted with 1,220mm-diameter ‘super-tube’ (twice the diameter of standard extension tubes) to increase stiffness and prevent deflection. Each of the four corners of the excavation is supported by a combination of MP150 and MP250 props in lengths ranging from just over 5m to more than 18m. These props act as knee-braces, supporting the Mega Brace beam at angles of approximately 45o. This arrangement imposes a significant shear force on the retaining wall. “At certain locations there are very short lengths of retaining wall comprising only a few piles and these are unable to resist the shear from the knee braces,” explains Groundforce Shorco major projects manager Adam Fletcher.  To enable the waling beam to resist the shear at these points, Groundforce Shorco designed bespoke steelwork that was welded to the Mega Brace beam in-situ. “When the final pile layout was determined we decided to split the frame to suit two levels of propping and designed a bespoke corner brace to follow the pile line and limit the deflection where shear keys could not be used,” explains Adam. Chiara Morena, Groundforce Shorco design manager, said: “In standard procedures, the props are located against the retaining wall using gallows brackets. These not only ensure the correct positioning of the prop but also carry its unsupported weight and prevent any risk of slippage. On this project, only the hard secant piles could be used for supporting the beam via gallows brackets and that was an additional challenge. Once a partial built wall was provided, we had to verify the anchored connection of the gallows brackets for each beam extension around the excavation. “However, due to the difference in level in the RCSI excavation, one of the MP250 props is installed at a 3o angle to the horizontal which introduces an upward force at the higher end of the prop as it is braced against the waling beam. To counteract this, we installed an additional gallows bracket upside down, in non-standard fashion, above the prop at this point.” Adam added: “Groundforce Shorco became involved when the design was at a very early stage and contributed to several revisions before the design was finalised, which also gave the opportunity to have a full picture of what was happening around the design. The bespoke solutions provided where the standard kit was not suitable are one of our strengths.” Damien Watson, project manager with Bennett Construction, commented: “Groundforce Shorco provided continuous assistance after completing the design and during the installation and removal phases. They even helped with elements that fell outside their responsibility as a supplier of temporary propping equipment.” Building, Design & Construction Magazine | The Choice of Industry Professionals

Read More »
Doka Formwork essential to the Delivery of High-Profile Scottish Harbour Extension

Doka Formwork essential to the Delivery of High-Profile Scottish Harbour Extension

Doka supplied the specialist formwork and technical support to facilitate a multimillion expansion of South Harbour in Aberdeen, the largest marine infrastructure project in Trust port history. The company worked in conjunction with contractor Beattie FRC on the harbour’s North Breakwater Crown Wall and surrounding main quay works. The overall aim of the ambitious development at the town’s largest harbour in Nigg Bay was to expand and diversify its use. The increased quayside space allows for more vessels to dock and significantly broaden trade opportunities around the North Sea. The 620m crown wall’s concrete construction was the result of detailed consultation between Doka and Beattie FRC. The contractor specified a two-pour solution in height involving 10m lengths boxes for what was an extremely largescale programme. With inclement weather a potential hinderance, the need for formwork that led to the wall’s construction within the client’s strict deadline was of the utmost importance. Doka had the knowhow and equipment to deliver the required solution. Equipped for building success  The Framax Xlife & Eurex 60 550 plumbing struts, MF240 platforms, WS10 Platforms from Doka were key to the safe, timely completion of the crown wall pours, which varied from 3m to 5.5m in height. The system’s rapid-forming capability was enabled by its optimised panel sizes which worked perfectly for the new desired pour heights. Furthermore, its forming times are kept to a minimum by widely-spaced form-ties of up to 1.35m apart. With the Framax Xlife unit, accuracy is not compromised for speed, with all connectors and accessories fitting seamlessly by the site team. On the crown wall quayside, the Doka MF240 climbing formwork optimised any on-site works as these were all assembled offsite by Doka in Sheffield. It meant that when they arrived at the site, they were almost immediately placed on the wall. The fully edge-protected, 2.40m-wide working platform enabled engineers regular, controlled access to the crown wall during its construction, as well as being able to plumb and align the Framax. Similarly, this process was duplicated for the WS10 platforms for the North Sea side of the wall. On this side of the wall the top pour contained a cope that had to be formed and supported. This helped inform the WS10 platforms’ design.  The cope’s load was transferred from the T7 spindles back to the platform and cast in wall anchors. This further intricate detail was easily accommodated by the range of quality Doka systems. The South Harbour’s expansion has achieved a number of beneficial outcomes. These include increasing the harbour’s water depth to 15m; enabled the berthing of 300m vessels; expanding laydown area to 125,000m2 and widening channel access to 165m. The harbour has opened to vessels, a number of which are docking at Nigg Bay for the first time thanks to the additional space the expansion has allowed. A huge investment that will profit the country as a whole, Doka is proud of its role in the regeneration of infrastructure that remains vital to the heritage and fiscal wellbeing of a grand Scottish town.   For more information visit doka.com Building, Design & Construction Magazine | The Choice of Industry Professionals

Read More »